The fire risk assessment lands in the inbox. It is packed with photographs, findings and recommendations. One communal fire door will not close properly, there may be a gap around a service pipe, and another issue needs further investigation. The report is finished. The work has barely started.
For managing agents looking after several residential blocks, the challenge is turning those findings into jobs that the right contractors can understand, price and complete. That sounds simple until the questions start arriving.
The door may need a fire door specialist. The service penetration may call for a fire stopping contractor. The third finding might need a closer look before anybody can quote. Filing all three under 'fire safety works' makes a tidy heading, but not much of a brief.
Take the instruction 'repair defective fire door'. Which door? What defect did the assessor observe? Is there a photograph? Was a timescale given? If answering those questions means reopening a 70-page PDF every time, even a straightforward quotation can become a small detective story.
A useful action register gives each finding its own reference and carries across the precise location, original wording, photographs and report page number. It also records the assessor's priority or timescale, who is responsible, and whether the item is awaiting clarification, quotation, instruction or evidence of completion.
The important distinction is between what the assessor actually said and what happens next. 'Investigate further' should not quietly become 'replace'. Where the solution is uncertain, the brief should say so; urgent concerns still need appropriate attention while details are resolved.
Two contractors can read the same vague request and price two different jobs. One assumes a replacement closer; another includes a survey and additional repairs. Their totals might look miles apart, even though neither has misunderstood the information supplied.
A clearer request includes the relevant findings, photographs, access arrangements and known constraints. It should also explain whether a site survey or specialist specification is required and what completion records are expected. Contractors can then make their inclusions, exclusions and assumptions explicit, making comparisons more meaningful than simply choosing the lowest figure.
And when the building has several similar defects, grouping work by trade can help, provided each door, floor or penetration remains identifiable. Nobody wants a completion note that says 'five doors repaired' when nobody can tell which five.
The contractor attends, the invoice arrives and the spreadsheet turns green. Tempting as that may be, payment alone does not demonstrate that the original recommendation has been addressed.
The action should be traceable from the assessment through instruction to suitable evidence of completion, such as photographs, records, certification or specialist confirmation where appropriate. A short close-out note can record who checked the evidence, when, and whether further inspection is required. If the work differs from the agreed scope, that change should be recorded too. Outstanding actions need owners and review dates, otherwise 'awaiting quotation' can become a permanent status.
Digital tools can take some of the copying and sorting out of the process, particularly when reports are lengthy. But extracted recommendations still need checking against the source document, and software cannot replace competent technical judgement.
A good assessment identifies the issues. Good follow-through makes sure they do not disappear into the inbox.
Dominic Came, Founder, Local Tenders